Climaticus markClimaticus Homepage
Irish farmland under an overcast sky, with hedgerow-lined fields and a line of electricity pylons crossing the horizon
Climaticus markThe Climaticus Brief

Fossil fuels met 79% of Ireland’s 2025 energy use: still no national exit date

Issue · 25 September 2026

By Katherine Casey, Climaticus

Authored by
Katherine Casey
Published by
Climaticus
Published
The Irish Times argued on 17 September 2026 that Ireland has still not set a target date for the full phase-out of fossil fuels, despite a measured decline in fossil fuel volumes since a 2008 peak 1. The Sustainable Energy Authority of Ireland reported in July 2026 that fossil fuels met 79.2% of the state's overall energy requirement in 2025, with imports covering 78.2% of that need and renewable energy reaching a record 15.9% share 2. Within that fossil total, imported natural gas, the same fossil fuel biomethane is built to displace on the grid, still accounted for roughly three-tenths of Ireland's energy use, and oil for close to half 1. Neither the newspaper's analysis nor the University College Cork energy modelling it draws on 3 names biomethane or anaerobic digestion as a distinct substitute for that gas share, and the omission matters because it leaves the one fossil fuel biomethane could most directly displace with no dedicated phase-out target of its own.

Section 1: Principal development

Ireland debates a fossil fuel exit date while its own gas replacement goes unnamed

The Irish Times published an analysis on 17 September 2026 arguing that Ireland has never set a target date for the complete phase-out of fossil fuels, despite a substantial decline in their use since a 2008 peak: coal and peat now sit below 13% of 2008 levels, and oil and gas together have fallen by a fifth, even as the population has grown by close to a quarter and the economy has expanded 1. The article draws on two primary sources. The Sustainable Energy Authority of Ireland's July 2026 energy security report put overall renewable energy at a record 15.9% of national demand in 2025, fossil fuels at 79.2%, and import dependency at 78.2%, with more than four-fifths of natural gas itself imported 2. University College Cork's Energy Policy and Modelling Group, in a 2050 pathways report published in September 2024, models an economy-wide shift built on electrification, projecting electricity's share of final energy to rise from 22% in 2020 to 41% by 2030 and 69% by 2040, with biogas appearing only as a minor input of roughly 3.2 TWh used within industry by 2030 under its mid-range scenario 3. Both documents are older than this week's news and are cited here as the evidence base the newspaper drew on, not as new developments in themselves.

The crux: Ireland has never published a target date for the complete phase-out of fossil fuels, and neither the Irish Times' own analysis nor the University College Cork modelling 3 it draws on names biomethane as part of how that date would be reached.

The stakes: Fossil fuels supplied 79.2% of Ireland's total energy requirement in 2025, oil close to half of that and imported fossil natural gas around three-tenths, against a renewable share that reached a record 15.9%, meaning four-fifths of the state's energy still runs on imported or extracted fuel with no published date by which that changes. The natural gas share matters specifically because it is the fuel biomethane displaces molecule for molecule on the grid, so a fossil gas share left unnamed in this debate is a biomethane opportunity left unnamed with it.

Who acts? The Department of Climate, Energy and the Environment, which owns the national energy policy framework and the Renewable Heat Obligation built to displace fossil heat with biomethane; the Sustainable Energy Authority of Ireland, which compiles the underlying statistics; and University College Cork's Energy Policy and Modelling Group, whose pathway work underpins much of the modelling in circulation.

What do they do? The Department can publish the target date the newspaper says is missing, and it can use that date to anchor the Renewable Heat Obligation's delayed commencement to a fixed point instead of the shifting practitioner assumption now in use.

Where the sector sits: Anaerobic digestion and biomethane are the only indigenous substitute for a meaningful share of the imported fossil natural gas that SEAI's own figures show still running through Ireland's grid, yet neither this debate nor the modelling behind it treats that substitution as a distinct pathway worth naming, folding it instead into a minor industrial input inside a much larger electrification story.
Interpretation: The mechanism connecting an unnamed phase-out date to a slow-moving biomethane sector runs through project finance. A lender or an equity investor pricing a twenty-year anaerobic digestion asset needs some fixed point against which fossil gas demand is expected to fall, because that decline is what eventually raises the value of the indigenous alternative competing against it. Where the state has published no such date, and where the modelling exercises informing policy treat biogas as a rounding error within an electrification-led pathway, the terminal demand curve for fossil gas has no anchor beyond general climate commitments that carry no obligation on any single sector to move by any single year. Developers are left underwriting biomethane's future value against a target that does not yet exist, using a Renewable Heat Obligation whose own commencement date has already slipped once. Naming a phase-out year would not itself finance a single digester, but it would give every financier currently guessing at the pace of fossil gas decline a number to guess against instead.

Section 2: Policy and regulation

The renewable gas certification registry marks its eighth year without a permanent home

Gas Networks Ireland's own account of its Green Gas Certification Registry traces the initiative to an innovation project first referenced in 2019, built on a 2018 sector blueprint, with first injections and a manual pilot registry established from 2020, formal appointment of Gas Networks Ireland as Issuing Body under Statutory Instrument 350 in 2022, and the Commission for Regulation of Utilities beginning supervisory engagement from 2023 5. The pilot has operated throughout on a spreadsheet-based system with manual processes. The CRU's decision paper of March 2026 committed Gas Networks Ireland to publishing finalised registration requirements for a permanent, automated registry no later than September 2026, with certificate issuance beginning no later than January 2027 6. Gas Networks Ireland's own most recently published project schedule sets tender issuance for the replacement software in May or June 2026, an implementation phase across the fourth quarter of 2026, and a go-live date only in the first quarter of 2027 5. With a week of September left at the time of writing, the finalised requirements the CRU committed to have not been published, and this issue could not confirm whether the tender scheduled for May or June was in fact issued on time.

Interpretation: Set against its own history, this year's slippage looks less like an isolated miss and more like the registry's established pattern. Eight years separate the original 2019 project reference from the go-live date Gas Networks Ireland's own schedule now targets, and every intermediate milestone along that path, the 2020 pilot, the 2022 statutory appointment, the 2023 supervisory engagement, the CRU's September 2026 publication commitment, has been followed by a later date replacing it before the earlier one was reached. A programme that resets its own internal schedule at roughly this rate is not obviously accelerating toward its stated destination, and a producer, trader or supplier planning around a January 2027 certificate issuance date should weigh that history before treating the current schedule as the one that finally holds.
Flag: Two dates for the Renewable Heat Obligation remain in circulation and neither has been formally reconciled. The Department's own account of the Renewable Heat Obligation Bill described legislation intended to provide a legislative basis for administering the scheme in 2026, at the point government approved its drafting. The European Commission's subsequent Detailed Opinion, questioning the scheme's indigenous-biomethane multiplier against internal market rules, has since pushed practitioner commentary toward treating 2027 as the working assumption for actual commencement. Both positions trace to identifiable primary sources, and the gap between the Department's stated 2026 ambition and the practitioner's revised 2027 expectation has not been closed by any new published timeline this issue could locate.

Section 3: Energy market

EU carbon allowances edge to €86 a tonne on the same secondary data this issue has tracked for six weeks

EU carbon allowances reached €86.01 a tonne on 23 September 2026, according to Trading Economics' tracking of the front-month ICE EUA futures contract, before easing 0.83% the following session 4. This is the fifth reading in this figure's series since April, when Trading Economics recorded €74.80: €83.80 on 4 September, €84.93 on 7 September, €85.34 on 11 September and now €86.01 on 23 September 4. Every one of those five readings comes from the same aggregator's tracking of front-month futures activity, and none has yet been checked against ICE's own published settlement data.

Interpretation: Five consistent readings from a single secondary source are not the same evidentiary base as five readings checked against an exchange's own settlement price, and this issue has flagged that gap in successive editions without yet closing it. A futures tracker can move on intraday activity that a settlement price does not reflect, and it can itself be revised after the fact in ways a reader following along week to week would not see. A biomethane or biogenic carbon dioxide project modelling revenue against a rising carbon price carries two distinct risks: the risk that the market genuinely moves against the assumption built into a contract, and the separate risk that the specific figure used to build that assumption was never the number that would actually settle a trade. Verifying this series against ICE's own data before it appears again would remove the second risk without needing to resolve the first.

Section 4: Carbon, MRV and climate claims

Brussels grants its own methane transparency database a delay Dublin was not granted for renewable gas certification

Trade coverage reported in mid-July 2026 that the European Commission had confirmed its EU Methane Transparency Database, intended to publish measured emissions data, drawn from direct monitoring rather than self-reported estimates, for oil, gas and coal placed on the EU market under Regulation (EU) 2024/1787, would launch in September 2026 rather than the February 2026 date the regulation originally set 7. The reported ten-month slip followed pressure from eleven member states seeking a longer transition period. This issue could not locate the Commission's own confirmation of the revised date at the time of writing and reports the figure here as trade coverage of an announcement whose underlying release was not publicly available. The database's scope is fossil fuels only: oil, gas and coal placed on the EU market carry the obligation, and biomethane and other renewable gas carry none of it.

Interpretation: The Commission that absorbed a ten-month delay to its own methane transparency obligation, with no infringement process reported, is the same Commission whose Detailed Opinion forced Ireland's Renewable Heat Obligation into a design overhaul rather than a simple postponement. This issue has not traced the distinct legal basis behind each outcome closely enough to say the comparison proves inconsistency, since a member-state transition request under an established regulation and a state aid question raised against a new support scheme are different procedural tracks. What is visible without that deeper tracing is the pattern in outcomes: a ten-month slip granted to incumbent fossil gas importers reads, to a biomethane developer watching both processes, as a flexibility its own sector was not offered when its central support mechanism came under the same Commission's scrutiny.

Section 5: Agriculture and Scope 3

The autumn closed period leaves a widening gap between digestate output and legal spreading windows

Teagasc's guidance on the 2026 closed period confirms that the prohibition on spreading chemical nitrogen and phosphorus fertiliser begins on 15 September in the most restrictive zone, that farmyard manure spreading must stop by 1 November, and that the autumn closed period for slurry and other organic manures begins on 1 October, with zone-specific reopening dates running from 12 January through to 31 January depending on location 8. Digestate from anaerobic digestion falls under the same organic manure rules as slurry in current guidance, and the published dates carry no separate provision for the volumes a plant continues to produce, and must store, once its own feedstock intake does not pause for the calendar.

Interpretation: A plant does not stop producing digestate because the spreading calendar has closed, and the arithmetic behind that fact is worth working through in full. Taking an illustrative processing rate of 100 tonnes of feedstock a day for a mid-sized facility, a closed period running from 1 October to the latest reopening date of 31 January spans roughly seventeen weeks, implying storage demand of more than ten thousand tonnes, calculated simply as throughput multiplied by that closed period's length, before any additional restriction tied to nutrient content is layered on top of the calendar restriction itself. A developer who sizes digestate storage against the shortest closed period in the state, rather than the longest closed period actually governing the land bank supplying or receiving from a given plant, is sizing against a number that understates the true requirement for any farm sitting in the more restrictive zone or spanning a zone boundary.

Section 6: Scholarly Spotlight

The finding

Rahic, Kelly, Karsten, de Lima Casseres dos Santos and Costello, publishing in Environmental Science & Technology in December 2025, ran a life cycle assessment of a simulated large Pennsylvania dairy farm adopting the "Grass2Gas" approach, combining continuous vegetative cover, manure management and anaerobic digestion 10. The modelled system reduced the carbon footprint of milk production by more than 20% relative to conventional management. The same modelling identified a direct trade-off: growing additional biomass for the digester to maintain year-round ground cover increased the farm's need for off-farm feed imports in most scenarios modelled, which offset a meaningful share of the water quality benefit the continuous cover was intended to deliver on a full life cycle basis. A further scenario, matching herd size to the feed a farm could grow on its own land, produced milk losses the authors describe as comparable in scale to typical waste already occurring elsewhere in the dairy supply chain.

The context

This week's agriculture section works through the storage arithmetic a closed spreading period imposes on a continuously operating digester; this paper works through a parallel arithmetic on the input side, showing that growing the biomass to keep a Grass2Gas-style system fed can itself generate an emissions and land-use cost large enough to erode the carbon benefit the system is built to deliver. Anyone treating anaerobic digestion's climate case as self-evidently positive once a digester is running is skipping the feedstock question this paper puts back on the table.

The limitation

The study is a simulation of one farm type in one American state, built on Pennsylvania's climate, land availability, feed markets and manure-management regulation, none of which map directly onto an Irish grass-based dairy system with different stocking rates, different rainfall patterns and a different regulatory closed period. The 20% figure describes an outcome reached in simulation, and no operating farm has yet measured it directly; the milk-loss comparison to supply chain waste is also one normative framing among several the authors could have chosen to describe the same underlying trade-off. A reader should treat the direction of the finding, that feedstock sourcing can erode digestion's climate benefit, as more transferable than the specific percentage attached to it.

The implication

A developer or an advisor promoting anaerobic digestion's climate credentials to a farmer or a buyer should be able to answer where the additional feedstock biomass comes from and what its own footprint is, not only what the digester itself achieves once fed. A system that improves on-farm carbon accounting by importing more feed from elsewhere is relocating emissions, not removing them, and the paper's own herd-size scenario suggests that matching feedstock ambition to what a farm can actually grow keeps that relocation from happening in the first place.

Rahic, E., Kelly, D., Karsten, H., de Lima Casseres dos Santos, L. and Costello, C. (2025) Integrating Continuous Cover, Manure Management, and Anaerobic Digestion Strategies on a Pennsylvania Dairy Farm: A Life Cycle Assessment. Environmental Science & Technology, 59(49), 26514–26525. https://doi.org/10.1021/acs.est.5c04797. Paywalled at the publisher; a plain-language summary is available from Pennsylvania State University's own research communications.

Section 7: Commercial opportunities

1. IrBEA National Bioenergy Conference
8 October 2026, Killashee Hotel, Naas, Co. Kildare
Running as two dedicated events under one umbrella for the first time in 2026, covering the bioenergy, biogas and biofuel sectors. 11
2. Global Bioeconomy Summit, Dublin
20 to 21 October 2026, pre-registration open
Held at the Convention Centre Dublin during Ireland's Presidency of the Council of the European Union. 12
3. Renewable gas Guarantees of Origin registration
Finalised requirements originally due no later than September 2026, now unmet; Gas Networks Ireland's own schedule targets go-live in the first quarter of 2027
Producers, traders and suppliers wishing to hold or trade certificates should confirm registration arrangements directly with Gas Networks Ireland and the CRU once published. 5
4. Ireland's second-round anaerobic digestion capital grant scheme
Market intelligence only, not a confirmed opening; trade press has expected an expression of interest process since Q3 2026, with no date yet published
Reported at up to €200m across the National Development Plan; applicants should verify directly with the Department. 13

Section 8: The Standing Watch

IssueStatus at 25 September 2026Movement
Renewable gas Guarantees of Origin registryFinalised requirements remain unpublished as September closes; Gas Networks Ireland's own schedule now targets a Q1 2027 go-live, with the intervening tender stage unconfirmedMoved
Renewable Heat Obligation commencementThe Department's original 2026 legislative-basis ambition and the practitioner's 2027 working assumption remain unreconciled; see this issue's flagUnchanged
Biomethane grid connection pipelineUnchanged since 18 September; three of seven contracted producers connected, combined developer-reported nameplate capacity of roughly 270 GWh against approximately 741 GWh under connection agreementsUnchanged
European biomethane sector consolidationNo further consolidation activity reported since Kanadevia Inova's 15 September acquisition of BioValueUnchanged
Green claims and climate neutrality claimsIreland's S.I. No. 124 of 2026 comes into operation 27 September 2026, two days after this issue publishes; CCPC enforcement approach not yet testedMoved
CBAM implementing detail and the Russia WTO challengeRussia's expected second panel request falls at the Dispute Settlement Body meeting of 25 September 2026, the day this issue publishes; automatic panel formation would follow if the request proceeds as expectedMoved
National AD planning guidanceKillough (case 500924) remains live with no decision recorded as of 24 September 9, against An Coimisiún Pleanála's own marker that it could not decide before 30 September; Corracunna remains undecidedUnchanged
Second-round AD capital grantsReported at up to €200m across the National Development Plan; no confirmed expression of interest dateUnchanged
Nitrates derogation review2026 derogation applications processed via Agfood portal; no further movement this weekUnchanged
CRCF methodology adoptionFirst permanent methodologies adopted 3 February 2026; Puro.earth certification programme openUnchanged
Ireland and the London Protocol export amendmentIreland not among ratifying states; Commission maintains the existing EU framework satisfies Article 6(2), contestedUnchanged

Section 9: Acting on it

1. A producer facing a registry that will not confirm compliance evidence before 2027 should build its own audit trail now, not wait on the state's.
This issue's account of the Guarantees of Origin registry's repeatedly reset schedule means a producer or trader needing to demonstrate provenance to a counterparty before the permanent system goes live cannot rely on that system's own timeline. Custos by Climaticus is built to hold exactly that kind of audit-ready feedstock and output record independent of any single national registry's go-live date, though whether a given producer needs it depends on what its specific counterparties are asking it to prove.
2. A developer sizing digestate storage should size it against the longest closed period actually governing its land bank, not the state's shortest.
This issue's agriculture section works the arithmetic showing that a seventeen-week closed period compounds directly into storage volume; a plant supplying or receiving from land in the most restrictive zone needs capacity calculated against that zone's calendar, not a more favourable one elsewhere in the state.
3. A developer or industry body responding to Departmental consultation should ask explicitly for anaerobic digestion's inclusion in any future phase-out target.
This issue's principal development shows that an unnamed exit date leaves indigenous gas with no forcing function distinct from the general climate commitments every fossil fuel already sits under; naming the sector inside a dated target is what would give project finance a fixed point to underwrite against.
Climaticus disclosureThe item above naming Custos moves from independent reporting into commercial commentary. Custos by Climaticus is a Climaticus offering, named only because this week's registry item concerns the traceability function it performs. This is not a claim that using it resolves a specific producer's compliance position, which depends on the facts of each case.

Sources cited in this issue

  1. The Irish Times, When will Ireland finally achieve full fossil fuel phase-out?, 17 September 2026: irishtimes.com ↩ ↩ ↩
  2. Sustainable Energy Authority of Ireland, Significant reliance on imported fossil fuels leaves Ireland exposed to global energy shocks despite renewable energy progress (First Look: Ireland's Energy Supply and Security of Supply 2025), 9 July 2026: seai.ie ↩ ↩
  3. University College Cork, Energy Policy and Modelling Group, Pathways for Ireland's Energy System to 2050, September 2024: ucc.ie ↩ ↩ ↩
  4. Trading Economics, EU Carbon Permits price data and commentary, 23 September 2026: tradingeconomics.com ↩ ↩
  5. Gas Networks Ireland, Innovation Project Reference Number 2019-020, Green Gas Certification Registry: gasnetworks.ie ↩ ↩ ↩
  6. Commission for Regulation of Utilities, Decision Paper CRU202615, Guarantees of Origin for Renewable Gas: Development of the Supervisory Framework, 24 March 2026: cru.ie ↩
  7. Petro Online, EU Methane Transparency Database now due in September 2026, European Commission confirms, 16 July 2026: petro-online.com ↩
  8. Teagasc, Fertiliser spreading: key dates approaching: teagasc.ie ↩
  9. An Coimisiún Pleanála, Case 500924 (Killough biomethane facility appeal): pleanala.ie ↩
  10. Rahic, E., Kelly, D., Karsten, H., de Lima Casseres dos Santos, L. and Costello, C. (2025) Integrating Continuous Cover, Manure Management, and Anaerobic Digestion Strategies on a Pennsylvania Dairy Farm: A Life Cycle Assessment. Environmental Science & Technology, 59(49), 26514–26525: doi.org ↩
  11. IrBEA, National Bioenergy Conference, 8 October 2026: nationalbioenergyconference.ie ↩
  12. Global Bioeconomy Summit 2026: gbs2026.org ↩
  13. Agriland.ie, Process for next round of biomethane capital grants to begin soon: agriland.ie ↩
Climaticus mark

Keeping up with Climaticus

Sign up to receive a monthly newsletter with the most important news and research from the briefings and beyond.

Your email will be used only to send the Climaticus monthly newsletter. You can unsubscribe at any time.